Japan To Abolish Fukushima Daini Nuclear Plant

31st July 2019 – Tokyo Electric Power Company Holdings Inc. officially decided Wednesday at a board meeting to abolish the Fukushima Daini nuclear complex near the Daiichi plant crippled by the March 2011 disaster.

It means that all 10 nuclear reactors in the northeastern prefecture, including the six at the Fukushima Daiichi complex, will be scrapped, though this will take decades. TEPCO President Tomoaki Kobayakawa met Fukushima Gov. Masao Uchibori and reported the decision.

The decommissioning work of the four nuclear reactors at the Daini plant will likely cost some 280 billion yen ($2.6 billion) and require more than 40 years.

Fukushima Daini nuclear power plant

The power company plans to build an on-site facility to store spent nuclear fuel from the plant, though it has yet to pick a final disposal site for the fuel.

The Daini complex started the four reactors’ commercial operation from 1982 to 1987. The nuclear power plant was also hit by the tsunami in the 2011 disaster, temporarily losing key cooling functions, but managed to avoid meltdowns that occurred at the Daiichi plant.

The prefecture has called for scrapping the Daini plant, saying its existence has been hampering reconstruction efforts.